projects-ares-murra-warra-blade-trailer
Ares Project Services have been awarded the inland transport and offloading scope for the upcoming Flyers […]
warradarge-ares-tower-platform-tracking
A proud milestone was achieved today as the final delivery of 3 wind turbine blades was […]
biala-ares-port-kembla-blade-discharge
Today was a significant milestone for the Biala Wind Farm project, with Ares successfully delivering the […]
warradarge-ares-tower-platform-forest
After nine months of non-stop deliveries, the final trailer load has been delivered to Warradarge Wind […]
murra-warra-ares-blade-pilots
After 15 months, over 700 total deliveries and plenty of challenges to overcome, Ares are proud […]
silverton-ares-bigfoot-tower
The last turbine component has been successfully delivered by Ares to Silverton Wind Farm. At over […]